June. Once
the layer of gravel is put down (a couple of inches thick),
an insulation barrier (think of plastic bubble wrap) is put
on top of it and then a thick wire mesh is put on top of
that. The mesh serves 2 purposes, a place to hold the radiant
tubes in place and as structural support for the concrete.
This was a back and forth thing between 2 contractors. The
gravel was put in by one contractor, then the barrier was
put in by the plumber, then the mesh by the original contractor,
then the tubes by the plumber, etc. Nobody wanted to be at
the house on the same day. Ugh. It was like herding cats.
Finally, a simple vapor barrier (10 mil plastic) was used
in areas where there wasn’t any tubing and not covered
by original insulation, like under the stairs. Then we passed
inspection and we were ready to pour the concrete.
June 23. The
pour. It’s an easy date
to remember because it’s Ali’s birthday. On that
day, a good old fashioned cement truck pulled up to the house
and dumped it’s cargo in the basement. On the left side
they poured in through an old basement window (that we have
since sealed up) using a temporary wooden trough. On the other
side, they poured in through the basement door. The main cement
layer (from the truck) was a sort of aggregate, very rocky,
and was several inches thick. After a couple of hours of drying,
they laid in on top of that about 1 - 2 inches of smoother
concrete (most likely from bags bought at Home Depot). All
of this was done in one day.
I got home that night and saw
my new basement floor...a clear 7 feet from the ceiling.
Since the slab was now below the top of the footing, the footing
was now exposed. So the guys reformed the exposed footing with
concrete.
July. Now
that the new floor was in, there was so much that could be
done. Simple put, without a floor you can’t have walls. Without walls, you can’t
have electrical and plumbing. So now we have the basement and
first floor framing put in.
On the first floor, the framing was simple. Close off the
bathroom, finish the closet space and fill in the spaces where
the radiators used to be. Originally the closet space was a
double closet...a door on one side at the top of the stairs
to the basement (still there) and a door on the other side
where the front door is (no longer there) with a wall in between.
Presumably, the same owner that put in the bathroom there took
out the wall and filled in the wall. So what we did was move
the wall on the front door side 16 inches in so we have a more
manageable depth to the closet and a nook on the other side
where we put a seat.
The electrician
wasn’t going to come until the framing
was done in the whole house. In the interest of getting things
done I had the electrician come when all but one wall wasn’t
up (the boiler room wall), which had one switch on it and the
electrician still complained. There was a lot of work to do
since the basement needed to be completely wired. We even had
upgraded our service from 100 amps to 200 amps (it’s
an old house...most have 150), to which the electrician once
again complained and tried to tell me I didn’t need 200
amps. I could use 100 amps for the basement alone. Just plain
laziness.
Begin rant. I’ve stayed away from any negative remarks
about the people we hired. After all, they all worked hard
and did anywhere from great to a phenomenal job...except the
electrician. There are so many things I can tell you about
these guys...it just kept adding up. Like why was the electrician
the only person who didn’t know to wire electrical lines
away from network and video lines (the framer knew this!).
It was a struggle just getting them to show up. The big thing
was they completely screwed up the lighting design I had for
the basement (I’m simplifying, but I wanted the stairway
on a separate switch than the rest of the theater). We only
found out in the end when all the walls were up and painted.
So what did he do? He argued with me telling me I never told
him to do it that way, believing that his guys can never screw
up. Meanwhile, he saw first hand a miswiring of the bathroom
fan...same situation. I told them one thing and they did another.
He didn’t argue with me after that. Luckily that light
was accessible from the attic and was fixed. The basement,
however, had to be wired to all one (four-way) switch. End
rant.
We had a small amount of electrical work done on the first
floor. A funny story here. There were 3 light switches (front
hall, living room front and living room back) that were just
off the floor, at the height of a regular convenience outlet.
Dimmers even. Why they were that way we didn't know at first,
but we found out...laziness. Apparently, the switches most
likely were outlets at first but converted to switches and
the wire from the switch to the light was not only a simple
extension cord, but it was buried in the plaster of the wall
or just behind the wood paneling. Talk about a fire hazard.
This was probably done by the same guy who took down the bearing
wall upstairs. Come to think of it, it's not that funny of
a story.
So we moved those switches up to a normal height, turning
their old positions back into outlets again, and turned an
outlet that was at switch height into a 3-way switch for the
living room. We also had a mystery switch in the kitchen near
the door. Since we couldn't figure it out, we turned it into
a 3 way switch for the kitchen light. This was one of those
things that we wondered why it was never there before. There's
a switch for the kitchen right next to the door now. Before,
if you entered through the kitchen, you had to walk through
the room and into the dining room in order to turn on the light.
We also moved the placement of the basement switch from outside
the stairs to inside. Made more sense this way, especially
since this was done before the whole lighting design fiasco
I previously mentioned.
The only exterior (and semi-exterior) work we had done was
move the main electrical conduit over by a foot. The main reason
for this was not only to move it further away from the kitchen
door, but to also make room for a larger mailbox. We also added
a new dedicated electrical line to the garage so now the door
opener isn't powered by a thin extension cord attached to the
light socket. Oh, this house was full of those things.
The plumber began roughing together the house in the end of
June and it continued on into July. Once we put the boiler
in, he was able to connect all the tubes from the floor and
the rest of the house. The laundry room was put together once
the studs were up on that wall, connecting the drain to the
pipe running under the slab and venting to the existing pipe
next to the stairs.
For both of the
second floor bathrooms we removed the flooring (which was
a couple of inches of concrete...bathrooms need extra support
to hold the weight of a full tub of water). For the master
bath, we opened the floor up and added more support on the
floor joists to essentially double the framing, since we
expanded into a room that was never a bathroom before. We
had to open it up anyway so the plumber can run the new lines
in the floor. It wasn't until after the plumbing inspection
where we could close the floor up.
As usual, while the workers were doing there thing, I was
doing mine...installing the network. Since the walls were open
I added network conduits. I could have just put the cable in
the walls, but the idea was to future proof it so I can take
away or add any type of cable without tearing down he walls.
Running from the wiring closet underneath the basement stairs,
I put in 5 conduits...7 if you count the ones buried under
the slab. Standing under the stairs facing out from left to
right, 1) goes to the back of the room where my office will
be, 2) goes to the left into the workshop for a future connection
into the kitchen, 3) goes to the right into the boiler room
and up the wall to behind the living room TV, 4) goes up through
the center closet following the plumbing stack up to the attic,
and 5) goes back and to the right to the center of the theater
room for a ceiling mounted projector...yes, but I'll get more
into the home theater stuff later.
Then after passing the plumbing, framing and electrical inspection,
we were ready to insulate. The first two passed with flying
colors, but in order to pass electrical we had to change all
our in-ceiling lights to IC rated (insulation connection, or
something like that) lights. What that means is more fire protection...good,
but significantly more expensive lights...bad.
The insulation guy
was the most efficient contractor I dealt with. He and his
crew were in and out in a day. They covered all exterior
exposed walls, plus a few more. That means the entire basement,
including ceiling (for added soundproofing), the 1st floor
bath, the entire master suite, and attic. There was never
insulation in the bedroom or attic before...and there’s
such a difference. The master suite (which is really one side
of the house) is warmer than the other side with original walls.
We passed the insulation inspection, we are ready to
close everything up.
The floor in the master bath was covered up with plywood immediately
because we had to walk on it. Now, the plumber could install
the tubs and had something to attach the radiant tubes to.
July
25th. Just over the border in Pennsylvania,
Wren is born. There were 4 puppies in that litter, and knowing
we wanted a girl all we had to choose from was the pattern
on her back. Things are going to get interesting in 10 weeks
when we bring her home.
Because we sold
our last place back in May, most of our stuff is in storage
and we've been practically living out of a suitcase at my
parents’ house since then. Every day without our
stuff was frustrating. We've been pushing to get to a point
where we could move in. All we really needed to move in is
one working full bathroom, and that would be done when the
stone floor is done so that is the goal. There's quite a few
thing to do until then, and even more after. It didn't help
that at the end of July I spent a week in San Diego for Comic-Con,
and 2 weeks later I was in Boston for a week during Siggraph.
So...
prev |1|2|3|4|5|6|7|8|9| next
Back
to the News page |